Tuesday, February 3, 2009

LOG 1- MP3

Tuesday, February 3rd
The beginning of this week was dedicated to creating a plan of procedures as far as construction is concerned and what needed to get done. A shopping list was also created and a date was picked to pick up supplies.

Tuesday, November 25, 2008

Log 5 MP2

Tuesday November 25th, 2008
Today in class I continued working on my dimensioned drawing of the floor plan. I was able too add in the necessary dimensions for construction.

Friday, November 21, 2008

Log 4 MP2

Friday November 21st
Today I was able to continue work on my floor plan and continue dimensioning. I have begun to dimension the interior of the building and the exterior. I had to go back and fix the exterior wall dimensions in order for them to be even measurements. After I finished this I was able to continue dimensioning. I need to be done with this drawing by the end of next week in order to stay on schedule.